Skip to main content
To KTH's start page

SAMBA 7 – Track stiffness and track maintenance

Researchers

  • Professor Mats Berg (Project leader)
  • Dr. Eric Berggren (Project leader)

Sources of funding

  • Banverket/Trafikverket

Research Direction

The overall aim of this project was to use measurement results of vertical track stiffness along the track to improve the track maintenance, in particular with respect to track irregularities.

The track stiffness was measured by a special-purpose rebuilt two-axled freight wagon running on the track at speeds up to 50 km/h and exciting one of the axles by harmonic or "white noise" loading. To some extent, results from ground penetrating radar was also used to suggest proper track maintenance actions or soil reinforce-ments.

The project was partly integrated with the EU project INNOTRACK, for instance by using the test wagon above on tracks in France and Germany.

Final report Samba 7 (in Swedish) (pdf 303 kB)

Belongs to: Department of Engineering Mechanics
Last changed: Nov 02, 2023
Gröna Tåget
Wheel profiles for freight wagons in Sweden (RV21)
Railway vehicle dynamics and track interactions: Total regulatory acceptance for the interoperable network (DynoTrain)
TOSCA
Crosswind stability and unsteady aerodynamics in vehicle design
A lightweight carbody for high-speed trains
Dynamic instability and discomfort of high-speed trains due to aerodynamics in tunnels
Influence of low-frequency vibrations on passenger activities
Modelling of rail vehicle dynamics
Robust safety systems for trains
Running gear for freight wagons
SAMBA 2 – Wear on wheels and rails
SAMBA 7 – Track stiffness and track maintenance
SimERT – Simulation of Energy consumption and Running Time
Train Information, Management and Monitoring (TIMM)