Project

Project description

An investor would like to investigate the options for the most profitable wind power investment. He asks different teams to perform pre-feasibility studies for different wind power projects. For more information please click Wind Power Project Description and Lecture on Project. 

Click the following links to download the file with all wind data and the file which can assist you in reading the data.

Wind data (.m files):

Read data (.m file)

Additional Information for part C

Project deliverables, in total three, should be submitted through the course web page on KTH Social. Please click “Assignments” in the menu to the left to view the deadline and for submission.

  • 25th Oct, Tuesday, 18:00h: upload project schedule
  • 6th Dec, Tuesday, 12:00h (noon/pm): upload final report
  • 6th Dec, Tuesday, 18:00h: report to be reviewed is sent out
  • 13th Dec, Tuesday, 8:00h: upload review report
  • 13th Dec, Tuesday, 13:00h-16:00h: team presentations

Project Presentation

A team presentation of 10–15 minutes, which will be held on Tuesday December 13, 2016, 13-16h. The presentation will be followed by questions from the audience, and the reviewer team.

For the ones who cannot, by different reasons, participate in the final presentation of the projects on December 13:

- The final presentation is compulsory, so if they are not available at that time, they have to do it later

- The final presentation consists of 2 parts:

a) make a presentation and answer questions: If the person is not present on December 13, the person has to contact Lennart, earliest on December 14* and then we can schedule a suitable presentation date/time.

*We do not know until December 13 how to organize this in detail since we do not know how many will not participate. It will probably not be possible to have all presentations before new year.

b) review another report and ask questions: For this part, these persons also have to state in the end of the presentation made later which extra report they have studied, and a summary of this report as well as some questions to it.

Concerning the final presentations on Tuesday December 13.
- Group 1-6: Presentations in room B2 

Presentation Opposition
Group 6 Group 1
Group 1 Group 2
Group 2 Group 3
Group 3 Group 4
Group 4 Group 5
Group 5 Group 6

- Group 8-13: Presentations in room B3

Presentation Opposition
Group 7 Group 13
Group 13 Group 11
Group 11 Group 9
Group 9 Group 10
Group 10 Group 8
Group 8 Group 7

- Prepare for MAXIMUM 12 minutes presentation
- Bring your own computer or USB stick to be used in a PC (not MAC)

Assistent Yalin Huang skapade sidan 25 juli 2015

Yalin Huang redigerade 16 september 2015

We are forming the groups for the project now. Please sign up for the project usingIf you have not registered on the internal list. Please do that. You can access the  link  here as well.

Yalin Huang redigerade 2 oktober 2015

We are forming the groups for the project now. If you have not registered on the internal list. Please do that. You can access the link here as wellProject description¶

An investor would like to investigate the options for the most profitable wind power investment. He asks different teams to perform pre-feasibility studies for different wind power projects. For more information please click wind power project.¶

Click the following links to download the file with all wind data and the file which can assist you in reading the data.¶

Wind data(.mat file)¶

Read data(.m file)¶

Reports should be submitted through the course web page on KTH Social. Choose “Submission project” below “Assignments” in the menu to the left. From this page you can upload your report latest Monday December 7, 2015, noon (12.00)
.

Yalin Huang redigerade 12 november 2015

Project description An investor would like to investigate the options for the most profitable wind power investment. He asks different teams to perform pre-feasibility studies for different wind power projects. For more information please click Wind Power Project and Lec_project.

Click the following links to download the file with all wind data and the file which can assist you in reading the data.

Wind data(.mat file)

Read data(.m file)

Project deliverables, in total three, should be submitted through the course web page on KTH Social. Please click “Assignments” in the menu to the left to view the deadline for each submission.



Project Presentation
A team presentation of 10–15 minutes, which will be held on Monday December 14, 10-12, 2015. The presentation will be followed by questions from the audience, and the reviewer team.

For the ones who cannot, by different reasons, participate in the final presentation of the projects on December 14:¶

- The final presentation is compulsory, so if they are not available at that time, they have to do it later¶

- The final presentation consists of 2 parts:¶

a) make a presentation and answer questions: If the person is not present on December 14, the person has to contact Lennart, earliest on December 15* and then we can schedule a suitable presentation date/time.¶

*We do not know until December 15 how to organize this in detail since we do not know how many will not participate. It will probably not be possible to have all presentations before new year.¶

b) review another report and ask questions: For this part, these persons also have to state in the end of the presentation made later which extra report they have studied, and a summary of this report as well as some questions to it.¶



Yalin Huang redigerade 11 december 2015

Project description An investor would like to investigate the options for the most profitable wind power investment. He asks different teams to perform pre-feasibility studies for different wind power projects. For more information please click Wind Power Project and Lec_project.

Click the following links to download the file with all wind data and the file which can assist you in reading the data.

Wind data(.mat file)

Read data(.m file)

Project deliverables, in total three, should be submitted through the course web page on KTH Social. Please click “Assignments” in the menu to the left to view the deadline for each submission.

Project Presentation A team presentation of 10–15 minutes, which will be held on Monday December 14, 10-12, 2015. The presentation will be followed by questions from the audience, and the reviewer team.

For the ones who cannot, by different reasons, participate in the final presentation of the projects on December 14:

- The final presentation is compulsory, so if they are not available at that time, they have to do it later

- The final presentation consists of 2 parts:

a) make a presentation and answer questions: If the person is not present on December 14, the person has to contact Lennart, earliest on December 15* and then we can schedule a suitable presentation date/time.

*We do not know until December 15 how to organize this in detail since we do not know how many will not participate. It will probably not be possible to have all presentations before new year.

b) review another report and ask questions: For this part, these persons also have to state in the end of the presentation made later which extra report they have studied, and a summary of this report as well as some questions to it.

Concerning the final presentations on Monday December 14.- Group 1-6: Presentations in room L42- Group 7-12: Presentations in room L43- Prepare for MAXIMUM 12 minutes presentation- Bring your own computer or USB to be used in a PC (not MAC)

kommenterade 20 oktober 2016

Page 7 of the project presentation: what are the differences between the different layouts? In particular, what are the differences between E1 and E3.

kommenterade 20 oktober 2016

Section D of the Project Description: we are given the number of lines, but not their impedance nor a means to calculating it.

Assistent kommenterade 21 oktober 2016

Page 7 of the project presentation refers to part C of the project description which states: "Calculate the annual energy production of the wind farm for the two layouts and the two wind turbine models ...". The images are meant to give exemplary combinations of the above.

For section D, you can calculate the impedance from the given parameters. You can also check the files in the References for the calculations.